# Footing Depth & Frost Rules Compared: 14 Countries, Mostly No Fixed Number

Minimum footing depth and frost-line rules compared across 14 countries — the one category where 'no fixed figure' is the norm, plus the two exceptions: India's flat 500mm and Japan's 240mm.

- Canonical HTML: https://www.chippy.tools/articles/footing-depth-and-frost-rules-by-country/
- Publisher: Chippy Tools
- Language: en
- Updated: 2026-11-09

# Footing Depth & Frost Rules Compared: 14 Countries, Mostly No Fixed Number

Sam Petherbridge · Qualified Carpenter & Builder

Updated November 9, 2026

Of the four comparisons we’ve run across our 14 countries — stairs, ceilings, ramps and now footings — this is the one where “no fixed figure” isn’t the exception, it’s the norm. Eight of the fourteen countries — New Zealand, Ireland, France, Germany, Spain, Indonesia, Norway and Sweden — explicitly defer minimum footing depth to a site investigation or a full Eurocode design process, with zero mandated centimetre figure in the national code. Only two countries buck that trend with a genuinely fixed nationwide depth: India, at a flat 500 mm, and Japan, at a 240 mm strip-footing embedment. Here’s how all fourteen actually handle it.

## Minimum footing depth & frost rule, by country

| Country      | Minimum depth / frost rule                                                                                                                                                                                                 | Governing standard / clause                                                                                                                                                                       |
|--------------|----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------|---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------|
| Australia    | **No fixed depth figure** — table/site-classification driven under AS 2870; 300 mm below finished ground level applies only on loose, erosion-prone sand                                                                   | [NCC 2025 Housing Provisions 4.2.2–4.2.3](https://ncc.abcb.gov.au/editions/ncc-2025/adopted/housing-provisions/4-footings-and-slabs/part-42-footings-slabs-and-associated-elements)               |
| USA          | 12 in / 305 mm minimum below grade (non-frost baseline); **frost-line depth is set locally** — the model code table is deliberately left blank for each jurisdiction to fill in                                            | [IRC 2021 R403.1.4 / R403.1.4.1](https://up.codes/viewer/connecticut/irc-2021/chapter/4/foundations)                                                                                              |
| New Zealand  | 200 mm minimum embedment OR to “good ground,” whichever is greater. **No frost-depth concept at all** — frost heave is instead handled by excluding any ground liable to ≥25 mm movement from the “good ground” definition | [NZS 3604:2011 s7.5](https://www.aucklandcouncil.govt.nz/content/dam/ac/docs/building-and-consents/ac2208-foundation-depth-for-buildings-outside-the-scope-of-nzs3604-2011.pdf) (via NZBC B1/AS1) |
| UK (England) | 450 mm minimum (frost, non-clay); 750/900/1000 mm on low/medium/high-shrinkage clay                                                                                                                                        | [Approved Document A (2013), para 2E4](https://assets.publishing.service.gov.uk/media/5a80437640f0b623026927b2/BR_PDF_AD_A_2013.pdf)                                                              |
| Canada       | Rock/coarse-grained soil: no limit. Clay/undefined soil: 1.2 m. **Frost depth itself is a local figure** — not a national NBC number                                                                                       | [NBC 2020 Table 9.12.2.2](https://free.bcpublications.ca/civix/document/id/public/bcbc2018/bcbc_2018dbp9s912)                                                                                     |
| Ireland      | **No fixed depth or frost-line figure** — set by ground/site investigation; width is table-driven (400–650 mm band)                                                                                                        | [TGD Part A 2012, par. 1.1.5.1–.3](https://www.gov.ie/en/publication/9d5d1-technical-guidance-document-a-structure/)                                                                              |
| France       | **No fixed national depth.** A climate-zone “hors-gel” (frost-free) system applies, but neither dual-verification pass could confirm a matching cm figure from primary text — no number ships                              | NF DTU 13.1 / NF P 94-261 — paywalled, no free primary URL                                                                                                                                        |
| Germany      | **No fixed national depth.** DIN 1054 gives 0.80 m as a general baseline assumption only; actual depth is site-determined, commonly 0.80–1.50 m in practice                                                                | DIN EN 1997-1 (Eurocode 7) + DIN 1054 — paywalled, no free primary URL                                                                                                                            |
| Spain        | **No fixed depth or frost-line figure** for an ordinary shallow footing — set by geotechnical study. (0.80 m applies only to retaining/basement walls, a different element.)                                               | [CTE DB-SE-C §4.2–4.3](https://www.codigotecnico.org/pdf/Documentos/SE/DBSE-C.pdf)                                                                                                                |
| Indonesia    | **No fixed depth, and no frost concept at all** (tropical climate) — depth set entirely by site/bearing-capacity investigation                                                                                             | [Permen PU 29/2006, Bab III.3.1.d](https://peraturan.bpk.go.id/Details/104487/permen-pupr-no-29prtm2006-tahun-2006)                                                                               |
| India        | 500 mm minimum below natural ground level — a genuinely **fixed national figure**; no numeric frost-depth rule (frost only a qualitative factor in fine sands/silts)                                                       | NBC 2016 Part 6 §6.2.2 — [bis.gov.in](https://www.bis.gov.in)                                                                                                                                     |
| Japan        | Strip footing: embedment ≥240 mm, base-slab ≥150 mm thick, stem ≥300 mm high/≥120 mm thick — a fixed national figure. Regional frost depth (Hokkaidō/Tōhoku) is set by prefectural/municipal ordinance, not national law   | [MLIT Notification No. 1347/2000, §一・4](https://www.mlit.go.jp/notice/noticedata/pdf/201703/00006441.pdf)                                                                                         |
| Norway       | **No fixed depth, frost, width or concrete-grade figure at all** — TEK17 explicitly and entirely defers foundation design to Eurocode 7/2                                                                                  | [TEK17 §10-2](https://www.dibk.no/regelverk/byggteknisk-forskrift-tek17/10/10-2)                                                                                                                  |
| Sweden       | **No fixed depth, frost, width, grade or cover figure at all** — the same full Eurocode deferral as Norway                                                                                                                 | [BFS 2024:6, Kap 7](https://www.boverket.se/sv/PBL-kunskapsbanken/regler-om-byggande/barformaga-stadga-bestandighet/geokonstruktioner/)                                                           |

## Deferring to site investigation is the majority position, not the exception

Eight countries — New Zealand, Ireland, France, Germany, Spain, Indonesia, Norway and Sweden — set no fixed centimetre figure for footing depth in their national code at all. Norway and Sweden are the most explicit about it: TEK17 and BFS 2024:6 both defer entirely to Eurocode 7’s site-specific geotechnical design process, with no fallback national number if you skip the investigation. That’s a genuinely different posture from a prescriptive “dig to 450 mm” rule — it puts the engineering judgement on the site conditions themselves rather than a nationwide average that would be wrong for a meaningful share of actual sites.

## India and Japan are the only two with a real fixed number

India’s NBC 2016 sets a flat 500 mm minimum below natural ground level, full stop — no soil-type banding, no frost adjustment, just a single national figure. Japan’s approach is more detailed but still genuinely fixed: a strip footing needs at least 240 mm of embedment, a 150 mm base slab, and a stem at least 300 mm high and 120 mm thick, all set by MLIT Notification No. 1347/2000. Notably, even Japan’s regional frost depth (relevant in Hokkaidō and Tōhoku) is set by prefectural or municipal ordinance rather than the national figure — so the embedment number is fixed nationally, but frost protection on top of it still varies by region.

## “Frost depth” is usually a local table, not a national number

Even in the countries that do set some kind of footing rule, frost depth specifically tends to drop out to a more local level. The US IRC deliberately leaves its frost-line table blank for each jurisdiction — the code structure assumes your local building department fills in the number that matches your actual climate. Canada’s NBC does something similar: the *depth* figures are national (no limit on rock, 1.2 m on clay), but the *frost* depth behind those figures is set locally. If you’re chasing a frost-line number for your project, your council or building department’s own table is very often the real source, not the national code itself.

## Check your own country’s full footing rules

The table above is the headline figures. Each country’s footings hub page covers width, concrete grade, cover and the full clause text:

- [Australia — footing sizes & site classification](https://www.chippy.tools/building-codes/au/footings/footing-sizes-site-classification/)
- [USA — footing sizes & depth](https://www.chippy.tools/building-codes/us/footings/footing-sizes-and-depth/)
- [New Zealand — footing sizes & depth](https://www.chippy.tools/building-codes/nz/footings/footing-sizes-and-depth/)
- [UK (England) — footing sizes & depth](https://www.chippy.tools/building-codes/uk/footings/footing-sizes-and-depth/)
- [Canada — footing sizes & depth](https://www.chippy.tools/building-codes/ca/footings/footing-sizes-and-depth/)
- [Ireland — footing sizes & depth](https://www.chippy.tools/building-codes/ie/footings/footing-sizes-and-depth/)
- [France — footing sizes & depth](https://www.chippy.tools/building-codes/fr/footings/footing-sizes-and-depth/)
- [Germany — foundation depth & footings](https://www.chippy.tools/building-codes/de/footings/foundation-depth-and-footings/)
- [Spain — footing sizes & depth](https://www.chippy.tools/building-codes/es/footings/footing-sizes-and-depth/)
- [Indonesia — footing depth & concrete](https://www.chippy.tools/building-codes/id/footings/footing-depth-and-concrete/)
- [India — footing sizes & depth](https://www.chippy.tools/building-codes/in/footings/footing-sizes-and-depth/)
- [Japan — footing depth & concrete](https://www.chippy.tools/building-codes/jp/footings/footing-depth-and-concrete/)
- [Norway — foundation depth & width](https://www.chippy.tools/building-codes/no/footings/foundation-depth-and-width/)
- [Sweden — foundation depth & width](https://www.chippy.tools/building-codes/se/footings/foundation-depth-and-width/)

## Get your footing concrete volumes right, whatever depth you end up digging to

Whether you’re digging to a fixed 500 mm figure or a depth set by your own site investigation, you still need to know exactly how much concrete to order once the trench is cut. Chippy Tools’ [concrete calculator](https://www.chippy.tools/features/concrete-calculator/) works out volume for footings, post holes and slabs in metric or imperial, so you’re ordering the right amount the first time.

### Skip the manual maths

Chippy Tools has professional calculators that handle these calculations for you — offline, on any device.

[![Download from the App Store](https://www.chippy.tools/images/download-badges/app-store/en.svg)](https://apps.apple.com/app/apple-store/id1579138717?pt=1325369&ct=chippy.tools&mt=8) [![Download on Google Play](https://www.chippy.tools/images/download-badges/google-play/en.png)](https://play.google.com/store/apps/details?id=tools.chippy&referrer=utm_source%3Dchippy.tools%26utm_medium%3Dwebsite)

## Frequently asked questions

Which countries set a genuinely fixed nationwide footing depth?

Only two, out of the fourteen we compared. India fixes a flat 500 mm minimum below natural ground level under NBC 2016 Part 6 §6.2.2. Japan fixes a strip-footing embedment of at least 240 mm, with additional fixed figures for base-slab thickness (≥150 mm) and stem height/thickness (≥300 mm/≥120 mm), under MLIT Notification No. 1347/2000.

Why do so many countries have no fixed footing depth?

Because footing depth genuinely depends on what's underneath the building — soil type, bearing capacity, groundwater, and (in colder climates) frost depth all vary by site and even by region within the same country. Eight of the fourteen countries here — NZ, Ireland, France, Germany, Spain, Indonesia, Norway and Sweden — explicitly hand that decision to a site investigation or Eurocode design process rather than mandating a single number nationally.

How is frost depth usually set, if not nationally?

Locally, in most of the countries where frost matters. The US model code (IRC) deliberately leaves its frost-depth table blank for each jurisdiction to fill in — Boise's frost line isn't the same as Minneapolis's. Canada's NBC does the same: rock or coarse-grained soil has no depth limit at all, clay/undefined soil needs 1.2 m, but the frost depth behind that figure is set locally, not nationally. Tropical countries like Indonesia skip the concept entirely — there's no frost to design around.

What should I do if my country's code sets no fixed footing depth?

Get a proper site or geotechnical investigation before you dig. Where a code defers to site conditions instead of a number, that's not an oversight — it's usually because a single national figure would be wrong for a meaningful share of sites. A soil test (or your local building authority's frost-depth table) is the actual source of the number you need, not a rule of thumb.