To calculate cubic yards of concrete, multiply your project’s length, width, and thickness in feet, then divide by 27 (because 1 cubic yard is 3 ft × 3 ft × 3 ft = 27 cubic feet):

Cubic Yards (yd³) = [Length (ft) × Width (ft) × (Thickness (in) ÷ 12)] ÷ 27

(Working in metric? Multiply Length (m) × Width (m) × (Thickness (mm) ÷ 1,000) to get cubic metres (m³) directly—or let the Chippy Tools Concrete Calculator handle both units automatically.)

Quick Reference Table: Concrete Yards Needed by Slab Size (4" & 6" Thick)

The table below gives both the exact net cubic yards and the recommended ready-mix order (+10% waste allowance), plus the number of 80 lb premix bags for smaller slabs:

Slab Dimensions (ft)Surface Area (sq ft)4" Thick Net (yd³)4" Order (+10% Waste)6" Thick Net (yd³)6" Order (+10% Waste)80 lb Bags (at 4" Net)
4 × 4 ft (Landing Pad)16 sq ft0.20 yd³0.25 yd³0.30 yd³0.35 yd³9 bags
8 × 10 ft (Small Shed)80 sq ft0.99 yd³1.10 yd³1.48 yd³1.65 yd³45 bags
10 × 10 ft (Patio Pad)100 sq ft1.23 yd³1.36 yd³1.85 yd³2.04 yd³56 bags
10 × 20 ft (Single Car Pad)200 sq ft2.47 yd³2.72 yd³3.70 yd³4.07 yd³112 bags
12 × 12 ft (Gazebo / Pergola)144 sq ft1.78 yd³1.96 yd³2.67 yd³2.93 yd³80 bags
12 × 24 ft (Single Garage)288 sq ft3.56 yd³3.91 yd³5.33 yd³5.87 yd³160 bags
16 × 20 ft (Workshop)320 sq ft3.95 yd³4.35 yd³5.93 yd³6.52 yd³178 bags
20 × 20 ft (2-Car Garage)400 sq ft4.94 yd³5.43 yd³7.41 yd³8.15 yd³223 bags
24 × 24 ft (Large 2-Car)576 sq ft7.11 yd³7.82 yd³10.67 yd³11.73 yd³320 bags
30 × 40 ft (Pole Barn / Shop)1,200 sq ft14.81 yd³16.30 yd³22.22 yd³24.44 yd³667 bags

Coverage Table: How Much Area Does 1 Yard of Concrete Cover?

When estimating on the fly, builders divide 27 cubic feet by the slab thickness in feet—or use the shortcut of 324 ÷ Thickness (in inches)—to find how many square feet 1 cubic yard covers:

Slab ThicknessThickness in FeetCoverage per 1 Cubic Yard (27 ft³)Coverage per 1 Cubic Metre (1 m³)Typical Application
2 inches (50 mm)0.167 ft162 sq ft20.0 m²Topping screed, crawlspace rat slab
3 inches (75 mm)0.250 ft108 sq ft13.3 m²Light garden footpath, mower strip
4 inches (100 mm)0.333 ft81 sq ft10.0 m²Standard patio, sidewalk, shed slab, car driveway
5 inches (125 mm)0.417 ft64.8 sq ft8.0 m²Heavy residential driveway, workshop floor
6 inches (150 mm)0.500 ft54 sq ft6.7 m²RV/boat pad, commercial apron, hoist bay
8 inches (200 mm)0.667 ft40.5 sq ft5.0 m²Heavy equipment pad, structural thickened edge
12 inches (300 mm)1.000 ft27 sq ft3.3 m²Structural footing trench, retaining wall base

Calculate Concrete Slabs, Post Holes & Stairs Offline

Download Chippy Tools on iOS or Android to calculate cubic yards, cubic metres, and bag counts in seconds—with zero ads.

Step-by-Step Worked Examples

Example 1: 20 ft × 20 ft Slab at 4 Inches Thick

  1. Convert thickness in inches to feet: 4 in ÷ 12 = 0.3333 ft
  2. Calculate volume in cubic feet: 20 ft × 20 ft × 0.3333 ft = 133.33 ft³
  3. Divide by 27 to convert to cubic yards: 133.33 ÷ 27 = 4.94 cubic yards net
  4. Add 10% waste allowance: 4.94 × 1.10 = 5.43 cubic yards (order 5.5 cubic yards from the batch plant).

Example 2: 24 ft × 24 ft Garage Slab at 4 Inches Thick

  1. Convert thickness to feet: 4 in ÷ 12 = 0.3333 ft
  2. Volume in cubic feet: 24 ft × 24 ft × 0.3333 ft = 192.0 ft³
  3. Convert to cubic yards: 192.0 ÷ 27 = 7.11 cubic yards net
  4. Add 10% waste allowance: 7.11 × 1.10 = 7.82 cubic yards (order 7.75 to 8.0 cubic yards).

Example 3: Round Post Holes & Sonotube Pier Footings (Cylinder Formula)

For circular post holes or Sonotube piers, use the cylinder volume formula (V = π × r² × Depth), where radius (r) is half the hole diameter:

Cubic Yards per Hole = [3.1416 × (Radius in ft)² × Depth (ft)] ÷ 27

Suppose you are pouring 10 deck piers, each 12 inches in diameter (radius = 6 in = 0.5 ft) and 42 inches deep (3.5 ft, below the frost line):

  1. Volume per pier: 3.1416 × (0.5)² × 3.5 = 2.75 ft³
  2. Total volume for 10 piers: 2.75 × 10 = 27.5 ft³
  3. Convert to cubic yards: 27.5 ÷ 27 = 1.02 cubic yards (or 27.5 ÷ 0.60 = 46 bags of 80 lb concrete).

(Note: If you are setting a timber post inside the wet concrete rather than sitting it on a top bracket, the Chippy Tools Concrete Calculator can subtract the submerged post volume automatically.)

Why Builders Always Add 5% to 10% Extra Concrete

Never order the bare theoretical net volume for a pour. Running 0.25 cubic yards short while the finisher is waiting with a bull-float means either scrambling to mix 12 bags of premix in a wheelbarrow (creating a visible cold joint and colour mismatch) or paying a $150–$300 short-load delivery fee for a second agitator truck.

Always add 5% to 10% extra to cover:

  • Sub-base low spots: Even a compacted gravel base that averages just 3/8 inch (10 mm) low across a 20 × 20 ft slab swallows an extra 0.46 cubic yards (21 bags) of concrete.
  • Formwork bow: Wet concrete weighs 150 lbs/ft³ (4,050 lbs/yd³) and pushes outward on timber edge boards between stakes.
  • Pump line & chute waste: Concrete pumps retain 0.25 to 0.5 cubic yards in the hopper and line at the end of a job.

Skip the manual maths

Chippy Tools has professional calculators that handle these calculations for you — offline, on any device.

Frequently Asked Questions

What is the formula for calculating yards of concrete?
Multiply Length (ft) × Width (ft) × Thickness (ft) to get volume in cubic feet, then divide by 27 to convert to cubic yards: Cubic Yards = (Length × Width × Thickness in feet) ÷ 27. If your slab thickness is in inches, divide the inches by 12 first (4" = 0.333 ft; 6" = 0.5 ft).
How much concrete do I need for a 20x20 slab?
A 20 ft × 20 ft (400 sq ft) concrete slab requires:
  • At 4 inches thick: 400 × 0.333 ÷ 27 = 4.94 cubic yards net (order 5.5 cubic yards with a 10% waste allowance).
  • At 6 inches thick: 400 × 0.50 ÷ 27 = 7.41 cubic yards net (order 8.25 cubic yards with a 10% waste allowance).
How much concrete do I need for a 24x24x4 slab?
A 24 ft × 24 ft slab at 4 inches thick (576 sq ft) requires 576 × (4 ÷ 12) ÷ 27 = 7.11 cubic yards net. Including a 10% allowance for sub-grade variations and spillage, order 7.8 to 8.0 cubic yards of ready-mix concrete.
How many square feet does 1 cubic yard of concrete cover?
One cubic yard (27 cubic feet) of concrete covers:
  • 108 sq ft at 3 inches thick
  • 81 sq ft at 4 inches thick
  • 64.8 sq ft at 5 inches thick
  • 54 sq ft at 6 inches thick
  • 40.5 sq ft at 8 inches thick
How many 80 lb or 60 lb bags of concrete make 1 cubic yard?
One cubic yard (27 ft³) of concrete requires 45 bags of 80 lb premix (each 80 lb bag yields 0.60 ft³), 60 bags of 60 lb premix (0.45 ft³ per bag), or 90 bags of 40 lb premix (0.30 ft³ per bag). In metric, 1 cubic metre (m³) requires roughly 108 bags of 20 kg premix.