The requirement
Water is the thing that wrecks a bathroom. So the rule book — the National Construction Code (NCC) — says which bits of a wet area you have to seal, and how well. There are two levels of sealing:
- Waterproof — a full barrier that water can’t get through. That’s your membrane.
- Water-resistant — the surface stands up to water but isn’t a sealed barrier.
The NCC asks for waterproof in the wettest spots and water-resistant in the splash zones. Here’s where each one goes (NCC 2025, clause 10.2).
Inside the shower (clause 10.2.2). This is the wettest part of the house, so nearly all of it has to be waterproof:
| Part of the shower | What’s required (NCC 2025) |
|---|---|
| The shower floor, including any hob or step-down | Waterproof |
| The shower walls, up to at least 1800 mm above the floor | Waterproof |
| Wall junctions (waterproof at least 40 mm each side) | Waterproof |
| Wall-to-floor junctions | Waterproof |
| Any penetrations (tap, waste, mixer) | Waterproof |
The 1800 mm wall height is set by the NCC itself — not by any standard. That’s the number to build to inside the shower.
- 1 shower floor
- 2 basin / bath
Outside the shower (clauses 10.2.3 and 10.2.5). Out here the rules ease off, and they change with what you’re building on:
- Floors are only water-resistant on a concrete or fibre-cement substrate. But on a timber-based substrate — particleboard or plywood — the floor must be fully waterproof. The material under your feet decides it.
- Walls next to a bath, basin or sink — any wall within 75 mm of that fixture — must be water-resistant to at least 150 mm above the fixture. This is the splash zone.
There is no single wall height for the whole room. It’s not “waterproof everything to X mm”. It depends on what the wall sits next to — 1800 mm inside the shower, 150 mm above a bath or basin, and nothing extra on a dry wall.
AS 3740 is optional. The NCC (clause 10.2.1) lets you follow AS 3740 — the wet-areas standard — as one way to get the job right. But it is not compulsory. You can instead follow the NCC’s own wet-area clauses (10.2.7 to 10.2.32). If you do take the AS 3740 path, follow it and the membrane maker’s instructions.
On site — what to waterproof
A quick run-through before you start rolling membrane:
- Shower floor — waterproof the whole floor, and don’t forget the hob or step-down.
- Shower walls — waterproof up to at least 1800 mm off the floor.
- Junctions — waterproof every wall junction (at least 40 mm each side) and every wall-to-floor junction.
- Penetrations — seal around the waste, taps and mixer.
- The floor outside the shower — waterproof it if it’s over a timber-based substrate; water-resistant is enough over concrete or fibre-cement.
- Walls beside a bath, basin or sink — water-resistant to at least 150 mm above the fixture, wherever the wall is within 75 mm of it.
- Membrane — follow the maker’s instructions, and AS 3740 if you’re on that path. The product’s own specs (coats, cure time, primer) come from the maker, not the code.
Related
- Part of the NCC rules for Australian chippies — the pillar, with the state-by-state adoption tracker.
- Building the room around it? See NCC minimum ceiling heights — the 2.1 m rule for bathrooms and laundries.
- Setting out the wet-area floor falls and drainage is a plumbing job — check with your plumber and the relevant plumbing standard.
Sources
- NCC 2025, ABCB Housing Provisions Standard, Part 10.2 “Wet area waterproofing” (clauses 10.2.1–10.2.32) — what must be waterproof vs water-resistant, the 1800 mm shower-wall height, the 40 mm junction rule, the 150 mm/75 mm rule at baths and basins, and the timber-vs-concrete floor split. Confirm at ncc.abcb.gov.au. (Confirmed against the NCC 2025 Housing Provisions Standard, verified 2026-07-28.)
- AS 3740 “Waterproofing of domestic wet areas” — an optional compliance path offered by NCC clause 10.2.1. It is paywalled; check the membrane and detail figures there (and your membrane maker’s instructions) if you use that path — do not treat any AS 3740 figure as a code minimum.
State variations
These states apply requirements that differ from the national provisions for this rule.
- Queensland Announced HP 10.2
Current code: NCC 2022
QDC and QLD wet-area provisions differ on floor wastes — confirm current MP/QDC position