The requirement
The building-type scope and full current annexes still need checking. The figures below are not a verified design for every house.
The cited text pairs 6° with 1:10 indoors, and 5° with 1:12 outdoors. These are not exact geometry conversions. A 1:12 slope is about 4.76°, while 1:10 is about 5.71°. Both limits sit in Permen PUPR No. 14/PRT/M/2017 (Persyaratan Kemudahan Bangunan Gedung), Lampiran II, its section on “Ram”, point 1.
The stair figures come from the same document. Confirm its mandatory and recommended provisions for the building before choosing a design.
The same document sets two more ramp limits:
- Goods or loading ramp: up to about 10° (point 14).
- Pedestrian curb ramp: a kerb ramp on a footpath, not a ramp into a building. It is capped at 6°, with a minimum width of 120 cm (point 10).
Landings, handrail & width
Landings. A ramp needs a level landing (bordes) at least every 900 cm (9 m) of run (point 6). The regulation shows a landing length in its own diagram. That figure lives only in the drawing, not in the written text. So we don’t print a landing-length number here. Size your landing with room to spare. Then check it against the diagram in the regulation itself.
Handrail. Every ramp needs a continuous two-tier rail on both sides (points 7 to 9 and 11). The lower tier sits at 650 mm for children. The upper tier sits at 800 mm for adults.
Width. A ramp needs a clear width of at least 95 cm (950 mm) without an edge kerb. With a kerb, the minimum is 120 cm (1200 mm). A fitted kerb must stand at least 10 cm (100 mm) high (points 2 and 3).
Work it out on site
You’re building a ramp to a house entry. The threshold sits 300 mm above the path. The ramp runs outside the building.
- Apply the outdoor limit. This example uses the cited 1:12 ratio. At 1:12, a 300 mm rise needs 300 × 12 = 3600 mm (3.6 m) of run.
- Check the landing rule. 3.6 m is well under the 900 cm (9 m) trigger for a mid-run landing. A level landing at the top and bottom is enough.
- Set the width. Go at least 950 mm clear if there is no edge kerb. Fitting a kerb? Make it 1200 mm.
So: 3.6 m of horizontal run at 1:12, with landings top and bottom, at least 950 mm wide. The slope calculator does the rise-over-run maths for you.
Do it in 5 seconds
Related
- Part of the Indonesian building-rules hub — one national framework, with the instruments that set the rules.
- Building the stairs that ramp might replace? See Indonesian stair rules.
Sources
- Permen PUPR No. 14/PRT/M/2017 (Persyaratan Kemudahan Bangunan Gedung), Lampiran II §2 (Ram), point 1 (indoor/outdoor gradient), point 2–3 (width and kerb), point 6 (landing interval), points 7–9 and 11 (handrail), point 10 (curb ramp) and point 14 (goods ramp). Read it at peraturan.bpk.go.id.
Read this first. These figures are from Permen PUPR 14/2017, issued under Indonesia’s pre-2017 Building Law framework. Later building legislation and implementing regulations need a current source check. UU 6/2017 is the Architects Law, not the Building Law. The regulation’s own Lampiran IV splits requirements into mandatory (“wajib”) and recommended (“disarankan”) by building type, and that table wasn’t available during research, so confirm which applies to your specific building. Always check the current instrument on pu.go.id or peraturan.bpk.go.id before you build to these figures.
Related building rules
More Indonesia rules
Ramps in other countries
- House Ramp Gradients: Choose the Right NCC Path
- US Ramp Slopes (IRC R311.8)
- NZ Ramp Gradients (NZBC D1)
- UK Ramp Gradients (Approved Document M)
- Canada Ramp Slopes (NBC 9.8)
- Irish Dwelling Ramp Gradients: TGD M Approach Rules
- French Ramp Rules: Housing Access and Terrace Exceptions
- German Ramp Gradients: DIN 18040-2 Accessible Ramp Rules
- Spanish Ramp Gradients: General Ramp vs Accessible Itinerary (CTE DB-SUA)
- Japanese Ramp Gradients: Slope, Landings & Width
- Indian Ramp Guidance: NBC 2016 Scope and Gradients
- Norwegian Ramp Gradients: TEK17 §12-16
- Swedish Ramp Gradients: Accessible Routes and the 1:12 Limit